• Call Us : 03082533000 (WhatsApp)
  • Email Us : TestPointpk.com@gmail.com
Sticky Note
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days?
  1. 24
  2. 25
  3. 26
  4. None of these
Explanation

Work done by 40 men in 40 days = 1/3 of total work

Total work = 3 × (40 × 40) = 4800 man-days

Remaining work = 2/3 of total work = 3200 man-days

Time left = 50 days

Men required = 3200 ÷ 50 = 64 men

Additional men needed = 64 − 40 = 24 men

Therefore, 24 more men are required.

Related MCQs

ایک MCQ کے لیے، اوپری گروپ میں درست کا تناسب 0.70 اور نچلے گروپ میں 0.55 ہے۔ D = p_u - p_l کا استعمال کرتے ہوئے، امتیاز انڈیکس کیا ہے
  1. +0.15
  2. -0.15
  3. +0.85
  4. -0.85
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. Rs. 1,891,000
  2. Rs. 1,892,000
  3. Rs. 1,890,000
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

تناسب کیا ہے؟
  1. The sum of two quantities
  2. The comparison of two quantities
  3. The difference between two quantities
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 30:1
  2. 300:11
  3. 25:1
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 1150
  2. 1350
  3. 1550
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com