40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days?
- 24
- 25
- 26
- None of these
Explanation
Work done by 40 men in 40 days = 1/3 of total work
Total work = 3 × (40 × 40) = 4800 man-days
Remaining work = 2/3 of total work = 3200 man-days
Time left = 50 days
Men required = 3200 ÷ 50 = 64 men
Additional men needed = 64 − 40 = 24 men
Therefore, 24 more men are required.
Related MCQs
ایک MCQ کے لیے، اوپری گروپ میں درست کا تناسب 0.70 اور نچلے گروپ میں 0.55 ہے۔ D = p_u - p_l کا استعمال کرتے ہوئے، امتیاز انڈیکس کیا ہے
- +0.15
- -0.15
- +0.85
- -0.85
اس سوال کو وضاحت کے ساتھ پڑھیں
- Rs. 1,891,000
- Rs. 1,892,000
- Rs. 1,890,000
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
تناسب کیا ہے؟
- The sum of two quantities
- The comparison of two quantities
- The difference between two quantities
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 30:1
- 300:11
- 25:1
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 1150
- 1350
- 1550
- None of these