X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone, and then after 4 days, Y joined him until the completion of the work. How long did the work last?
- 10 days
- 6 days
- 15 days
- None of these
Explanation
X can do the work in 20 days, so X's work rate is 1/20 of the work per day.
Y can do the work in 12 days, so Y's work rate is 1/12 of the work per day.
X works alone for 4 days, completing 4/20 = 1/5 of the work.
Y joins X, and together they complete the remaining 4/5 of the work.
Their combined work rate is (1/20 + 1/12) = 8/60 = 2/15 of the work per day.
Since they complete 4/5 of the work together, it takes them (4/5) / (2/15) = 6 days to complete the remaining work.
Adding the 4 days X worked alone, the total duration is 4 + 6 = 10 days.
So, the correct answer is: 10 days.
Related MCQs
- 25
- 35
- 45
- 55
اس سوال کو وضاحت کے ساتھ پڑھیں
- 50 worker-days
- 60 worker-days
- 65 worker-days
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 50
- 45
- 40
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 5 km
- 3 km
- 4 km
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 2 km
- 3 km
- 4 km
- 5 km