If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be ____?
- 12
- 8
- 10
- None of these
Explanation
10 men can do it in 12 days
1 man would take 10 × 12 = 120 days
12 men will take 120 / 12 = 10 days