5 men can do a work in 50 days. How long will it take 3 men to complete the work?
  1. 80 days
  2. 82 days
  3. 83 days
  4. 85 days
Explanation
5 men = 50 days
1 man = 5 × 50 = 250 days
3 men = 250/3 = 83.33 days

Last verified on 02-03-2026