If 30 men working 9 h per day can reap a field in 16 days, in how many days, will 36 men reap the field working 8 h per day?
- 15
- 251
- 10
- 18
Explanation
Here M1 = 30, D1 = 16,
T1 = 9, M2 = 36 and T2 = 8
By formula, M1D1T1 = M2D2T2
30 x 16 x 9 = 36 x D2 x 8
∴ D2 = (30 x 16 x 9)/(36 x 8) = 15 days